Connection steps in WA (household view)
Five steps take your solar and battery from design approval to switched on. Here is who does what, and the one step where you need to act.
At a glance
- Steps to switch-on
- 5
- Approval, offer, install, commissioning, turn-on
- Your action
- Step 2
- Read and accept the offer
- Papers to keep
- 3
- Model numbers, commissioning report, VPP steps
The five steps
Pre-approval
InstallerYour installer submits the design with model numbers.
Offer
YouYou receive export and inverter capacity terms to accept. Check the approved export limit on the offer.
Install day
InstallerHardware mounted, AC/DC wiring, protection, labelling.
Commissioning
InstallerInverter settings made, including the WA grid setting (Region B), and network tests.
Metering and turn-on
Retailer + networkRetailer and network actions, then app setup and handover to you.
After switch-on: 21 days of monitoring
Keep a copy of
- The final model numbers
- The commissioning report
- Any VPP enrolment stepsOnly if you plan to join a VPP.